A fountain/water feature was constructed at the entrance of the newly built head office of Deloitte and the need to waterproof the concrete structure arose, since it’s a water retaining type and could experience leakages.
PROJECT DETAILS
CLIENT
Ronald Ward & Associates
OVERVIEW
Waterproofing of:
Fountain/Water features
PRODUCTS USED
Xypex Concentrate
COVERAGE AREA
WATERPROOFING SOLUTIONS
The concrete structure was waterproofed with Xpex Concentrate and left to cure for 15 days.